Repair of 0.4kV switching station and electrical control room
PGNiG TERMIKA SA Siekierki Power PlantProject
Repair of 0.4kV switching station and electrical control room
Deadline
2017
PGNiG TERMIKA SA Siekierki Power Plant
Leader of changes in the heating sector. The largest producer of heat and electricity in cogeneration in Poland. It constantly improves production and management processes that increase the effectiveness and value of the company. It strives for operational excellence.
Services
Electricity, energetics:
- overhaul and modernization according to the client's requirements
Industry
Commercial power industry
Project engineer
Paweł Perłowski
(+48) 668 022 097
pawel.perlowski@konrem.pl
"The investment was closely tied to the schedule created by the Investor and timely completion of the project was crucial. Close cooperation with the Investor during the implementation of the task."
Challenge
- overhaul of 0.4kV switching station and electrical control room
Solution
- overhaul of KOI 0.4kV switching station
- review of FAT inverters
- inspection and maintenance of the primary circuits of 0.4 kV switching station
- checking linear and clutch protection as well as transformer measurements
- overhaul of the R110kV generator control and signaling system
- repair of frequency converters of K11 and K15 boilers
- execution of ordered overhaul works
- execution of commissioned inspections and maintenance
- measurements
- transfer of research results and reports from completed works
Result
- improving the reliability of the devices
- increasing work safety
- preparation of equipment for the heating season
- restoring the efficiency of the equipment