Overhaul of carburising system equipment

PGNiG TERMIKA SA Żerań CHP Plant

Project

Overhaul of carburising system equipment

Deadline

2015

PGNiG TERMIKA SA Żerań CHP Plant

Leader of changes in the heating sector. The largest producer of heat and electricity in cogeneration in Poland. It constantly improves production and management processes that increase the effectiveness and value of the company. It strives for operational excellence.

Services

Mechanics:
- overhaul and modernization according to the customer’s assumptions or with technical support (audit)
- production of spare parts

Industry

Commercial power industry

Project engineer

Adam Madej
(+48) 668 022 095
adam.madej@konrem.pl

"The investment required a quick reaction due to shutdown of individual devices in the power plant and was closely tied to the schedule."

Challenge

  • planned overhaul of carburizing equipment
  • replacement, restoring and maintenance of carburizing equipment elements in accordance with detailed work schedule

Solution

  • overhaul of belt conveyors
  • overhaul of coal crushers
  • overhaul of coal unloading infrastructure

Result

  • extending the service life of the main carburising equipment
  • ensuring proper functioning of the equipment
  • restoring full efficiency of the devices