Modernization of ash tank pumps
PGNiG TERMIKA SA Siekierki Power PlantProject
Modernization of ash tank pumps
Deadline
2016
PGNiG TERMIKA SA Siekierki Power Plant
Leader of changes in the heating sector. The largest producer of heat and electricity in cogeneration in Poland. It constantly improves production and management processes that increase the effectiveness and value of the company. It strives for operational excellence.
Services
Power industry, telecommunications engineering:
- overhauls and modernization according to customer’s assumptions or with technical support (audit)
- projects and visualizations of superior systems (SCADA systems)
- projects and installing automation system and control & measurement devices
Industry
Commercial power industry
Project engineer
Adam Madej
(+48) 668 022 095
adam.madej@konrem.pl
"The investment required a quick response to tasks and efficient work organization, due to the need for shutdown of individual devices in the CHP plant."
Challenge
- modernization of ash tank pumps
Solution
- execution of projects in the electrical, mechanical and I&C industries
- cooperation with UDT (the Office of Technical Inspection) and ensuring commissioning of pumps by UDT
- disassembly of old pumps and control cabinets
- assembly of new pumps with control and power supply
- test run of pumps
Result
- increasing efficiency of the ash removal system due to the use of new pumps
- increased failure-free performance of the pump system