Mechanical repairs of the K10 electrostatic precipitator
PGNiG TERMIKA SA Siekierki Power PlantProject
Mechanical repairs of the K10 electrostatic precipitator
Deadline
2017
PGNiG TERMIKA SA Siekierki Power Plant
Leader of changes in the heating sector. The largest producer of heat and electricity in cogeneration in Poland. It constantly improves production and management processes that increase the effectiveness and value of the company. It strives for operational excellence.
Services
Mechanics:
- overhaul and modernization according to the client's instructions
Industry
Commercial power industry
Project engineer
Paweł Perłowski
(+48) 668 022 097
pawel.perlowski@konrem.pl
"The investment was closely tied to the schedule created by the Investor and the timely completion of the task was crucial. Detailed cooperation with the Investor during the task implementation."
Challenge
- mechanical overhaul of the K10 electrostatic precipitator at the Siekierki Combined Heat and Power Plant in Warsaw
Solution
- execution of commissioned works - replacement of collecting electrodes with new ones with delivery
Result
- improvement of equipment reliability
- increasing the work safety
- preparation of the equipment for the heating season
- restoring the efficiency of the equipment