Execution, delivery and assembly of complete belt conveyor drives
PGNiG TERMIKA SA Żerań CHP PlantProject
Execution, delivery and assembly of complete belt conveyor drives
Deadline
2015
PGNiG TERMIKA SA Żerań CHP Plant
Leader of changes in the heating sector. The largest producer of heat and electricity in cogeneration in Poland. It constantly improves production and management processes that increase the effectiveness and value of the company. It strives for operational excellence.
Services
Power engineering, telecommunications engineering:
- project and construction of technological lines and equipment
- projects and visualizations of superior systems (SCADA systems)
- projects and installing automation system and control & measurement devices
Industry
Commercial power industry
Project engineer
Adam Madej
(+48) 668 022 095
adam.madej@konrem.pl
"The investment required a quick reaction due to shutdown of individual devices in the heating plant was closely tied to the schedule."
Challenge
- delivery, assembly and launch of drives of T10II and T11II inclined belt conveyors
Solution
- execution of works in the electrical, mechanical and I&C area
- disassembly of old drives and power supply
- assembly of new drives together with electrical and I&C
- launch of new belt conveyor drives
Result
- extending the service life of the main carburising devices in the CHP plant
- ensuring proper functioning of carburising equipment
- the ability to operate the conveyor at two speeds