Leader of changes in the heating sector. The largest producer of heat and electricity in cogeneration in Poland. It constantly improves production and management processes that increase the effectiveness and value of the company. It strives for operational excellence.

Services

Mechanics:
- renovation and modernization according to client's instructions or with technical support (audit)
- production of technological equipment and spare parts

Industry

District heating

Project engineer

Adam Madej
(+48) 668 022 095
adam.madej@konrem.pl

"The investment required a quick response due to the withdrawal of individual devices in the power plant. The investment was closely tied to the schedule."

Challenge

  • comprehensive overhaul of carburizing and dust extraction equipment
  • performing the necessary accompanying and finishing works

Solution

  • overhaul of the WRK crane construction
  • repair of ZRP devices (gutters, aeration lances, screw conveyors, etc.)
  • replacement of hot drain pipelines

Result

  • extending the service life of the main carburizing installations and dust extraction in the heat plant
  • ensuring proper functioning of carburizing devices in the heat plant
  • restoring full efficiency of the devices
  • ensuring proper functioning of dust extraction system